Challenge
WSP with joint venture partner Cummins was engaged by the U.S. Army Corps of Engineers to provide safe and reliable power on the U.S. military’s most remote remaining Forward Operating Base while meeting its growing power demands.
Solution
WSP and its joint venture partner Cummins designed and installed a 5 MW power plant, expandable to 7 MW. The plant was successfully commissioned in just 45 days, which required seven Ilyushin IL-76 air charter flights originating from Dubai and various in-country flights and line haul ground missions originating from Bagram Airfield and Kabul directly into FOB Dwyer. To perform aircraft offloading at Dwyer, WSP personnel mobilized dedicated material handling equipment flown in from Kandahar. WSP is currently ensuring safe operations and maintaining the power plant and the base-wide primary electrical distribution system.
This facility marks the 15th power plant project for the joint venture in Afghanistan since 2011, bringing the total in-country portfolio to 200 MW.